KBOI Staff

KBOI Staff
BOISE, Idaho - (via press release from Idaho Transportation Department)

The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.
BOISE - Interstate 84, Cole Road to Broadway Avenue widening
I-84 drivers now have four eastbound and four westbound lanes, double the pre-construction capacity. The two-year reconstruction project in this area has included installing new drainage, replacing the original two-lane pavement from 1968, and adding two new lanes in both directions.
The speed limit has returned to 65 mph for the first time since construction started in late 2009.
Overhead signs will be placed in early 2012 near the Vista Interchange, completing the project. A series of lane closures will accompany this work.
Concrete Placing Co. Inc., of Boise, is the contractor on the $35.9 million project.
NAMPA - I-84 widening, Franklin to Garrity
In Nampa, the project to widen Interstate 84 between the Franklin and Garrity Boulevard interchanges is progressing toward completion in early 2012.

On a section of westbound I-84, temporary concrete railing has been replaced with construction barrels, which will remain in place until the project is complete.

Crews continue to work on two new bridges spanning the Union Pacific Railroad and the Phyllis Canal.

Other construction activity to expect includes shoulder paving, overhead sign and lighting installation. Intermittent nighttime lane reductions may be necessary on I-84. All lanes remain open during the day, and work may be weather dependent.

The I-84 eastbound on-ramp at Franklin Boulevard remains closed until the interstate widening project is complete. Motorists are advised to use an alternate route for eastbound interstate access, such as the Northside or Garrity interchanges - each is approximately one mile from the Franklin interchange.

Once these interstate improvements are complete, I-84 between Franklin and Garrity will be widened to three lanes in each direction, with an additional auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the farthest right lane, and exit at Garrity - never having to merge with interstate traffic.

Concrete Placing Co. Inc., of Boise, is the contractor on this $22.2 million project.

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

BOISE COUNTY
EAST OF BOISE - Mores Creek Bridge upgrade
A project to update the Mores Creek Bridge (commonly known as the High Bridge) on Idaho 21 east of Boise is under way. The project should be done by the end of April 2012.
During this work, the bridge deck and joints will be rehabilitated and the bridge parapet and railing replaced. Work on the foundation during the low-water winter period will include a retaining wall, rock anchoring, slope armoring, and seismic retrofit. Portions of the structural steel will be painted along with other repairs on the structure.
Traffic across the bridge is controlled by signals at either end, with only one direction allowed to pass through at a time. Under normal conditions, the delays are expected to be 15 to 45 minutes in length. In addition, a nine-foot width restriction will be in effect.
Crews continue drilling for rock anchors and permeation grouting.

Traffic has been switched to the east side. The nine-foot width restriction remains in place, and the contractor is doing work below bridge on piers and down at footings. Workers may not be visible from the roadway, but they are present.

Work remains in a one-lane configuration.

RSCI, of Meridian, is the contractor on the $2.8 million project.
NEAR LOWMAN – Fish-passage project
A fish-passage project east of Lowman began June 15 and will continue through mid-December.
The bridge is in a one-lane configuration using a traffic signal.

This week, the contractor installed guardrail on the southbound side of the bridge. Crews will prepare to open the deck to traffic late next week.

Crews anticipate working a Monday through Thursday, 7 a.m. to 5 p.m. schedule.
This project is being funded through the U.S. Forest Service.
Cannon Builders Inc., of Blackfoot, is the contractor on this $1.2 million project.
PAYETTE COUNTY
PAYETTE – U.S. 95, Payette River Bridge replacement
The project to improve the U.S. 95 bridge over the Payette River south of Payette is under way. It is expected to take about two years to complete, finishing in summer 2012.
Crews are replacing the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts as the current one does and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.
The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.
U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.
Traffic has been switched to the northbound bridge. Work is proceeding on the old bridge and southbound lanes. Guardrail demolition, asphalt removal and other clearing is under way. Construction of the storm drain is complete.

Utility companies have relocated their facilities to the new conduit on the new bridge, while the conduit on the old bridge is being removed. Containment and protection systems are being installed as a precursor to removal of the deck from the old bridge.

JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.